Hezhou Huarun Circular Economy Industrial Demonstration Area Photovoltaic Power Generation Project
Construction, equipment installation and commissioning
Tender Notice
Tender Notice ZBGG201612319
Entrusted by the tenderee, the tender invitation for the construction of the photovoltaic power generation project in the Huazhou Cycling Economy Industrial Demonstration Zone in the 7th batch of China Resources Power South China Area 2016 and the installation and commissioning of the equipment were conducted.
I. Basic situation of the project
Tenderee: China Resources Power (Hezhou) Co., Ltd.
Project Location: Linshan Town, Fuchuan Yao Autonomous County, Hezhou City
Project funding source: self-raised
Overall progress of the project: see the tender documents
Second, the tender situation and bidder qualification requirements
(a) the tender number: S04019816GZ0006XM
(B) Title: Construction, Equipment Installation and Commissioning
(III) Tenderee: China Resources Power (Hezhou) Co., Ltd.
(IV) Bidding content and scope: Photovoltaic power generation project site of Hezhou Huarun Recycling Economy Industry Demonstration Zone Roads, pile foundation works, photovoltaic module foundations and supports, current collection lines, grounding, photovoltaic components and equipment installation and debugging projects, etc. specification)
(5) Qualifications and performance requirements of bidders:
1. Must have the qualification of enterprise legal person of the People's Republic of China.
2. Must have a valid safety production license.
3, must have a power engineering construction general contracting grade or above qualifications.
4. The bidder must have 3 or more wind power or photovoltaic power plant project construction achievements of the same type for the past three years (referring to the 36 months before the deadline for bid submission), and provide the contract homepage, contract scope page, contract signature stamp page Copies and other proofs.
5. Project Manager: Must have a Class 1 Registered Construction Professional Qualification Certificate (construction or electromechanical specialty) with 1 or more performance of the same type of wind power or PV power plant engineering project manager.
6, does not accept the Commonwealth bid.
(VI) Main indicators:
(VII) Delivery/Construction Date: Planned Commencement Date: February 16, 2017
Planned Completion Date: June 09, 2017
(8) Remarks:
Note: Please refer to the bidding documents for details. The bidding documents shall prevail.
Third, the issue of tender documents
(I) Time and place of sale
December 30, 2016 - January, 2017
Basic Physics Experiment Instrument Series
Basic physics experiment instrument series, used in physics laboratories of colleges and universities.
Basic Physics Experiment Instrument,Light And Optical Instruments,Optical Viewing Instrument,Microscope Light Source Instrument
Yuheng Optics Co., Ltd.(Changchun) , https://www.yhencoder.com